Answer:
Optimistic duration
Step-by-step explanation:
The following three concepts are Project management concepts:
Optismitic duration: Estimation of the shortest duration of a task, taking into account the difficulty, etc.
Pessimistic duration: Estamation of the longest duration of a task, taking into account the difficulty, etc
Expected duration: Expected duration of a task, kind of a compromise between the optmistic duration and the pessimistic duration.
Which of the following is the estimate of the minimum amount of time it would take to perform a task?
The answer is Optimistic duration