Answer:
Technology
Step-by-step explanation:
The three most important task requirements cost, schedule and time - are now and then known as the triple constraints or the triangle of project management. An undertaking's scope includes the particular objectives, expectations and assignments that characterize the limits of the task.
There are 6 project constraints and these include Cost, Quality, Benefits, Risk, Scope and Time.
Thus Technology is not a part of constraints.