Which of the following is NOT shown on a PERT chart? (Points : 2) Scheduled start date

Actual start date
Task name
Estimated duration
Intertask dependencies

User Zoinky
by
7.5k points

1 Answer

0 votes

Answer:

Estimated Duration

Step-by-step explanation:

A PERT Chart is a tool in Project Management that gives a graphical portrayal of an undertaking's timetable. The Program Evaluation Review Technique abbreviated as PERT separates the individual assignments of a venture for investigation.

The most widely recognized components utilized in a PERT chart are:

  • Span time.
  • Activity
  • Early finish time.
  • Early Ending time
  • Late initiation time.
  • Late completion time.
  • Critical path
  • Slack.

It does not include the Estimated span of time.