Ann Chovies, owner of the Perfect Pasta Pizza Parlor, uses 20 pounds of pepperoni each day in preparing pizzas. Order costs for pepperoni are $10.00 per order, and carrying costs are 4 cents per pound per day. Lead time for each order is three days, and the pepperoni itself costs $3.00 per pound. If she were to order 80 pounds of pepperoni at a time, what would be the length of an order cycle?(A) 4 days(B) 5 days(C) 3 days(D) 0 days(E) .25 days

User Pynchia
by
6.5k points

1 Answer

4 votes

Answer:

Option (A) is correct.

Step-by-step explanation:

Given that,

Order costs for pepperoni = $10.00 per order

Carrying costs = 4 cents per pound per day

Lead time for each order = 3 days

Pepperoni itself costs = $3.00 per pound

Total Order = 80 pounds of pepperoni

Demand rate = 20

Total ordering cost = Total order × cost per order

= 80 × $10

= $800

Length of an order cycle:


=(Order\ quantity)/(Demand\ rate)


=(80)/(20)

= 4 days