Answer:
The answer is: The overhead variance was $1,700 and it was overapplied
Step-by-step explanation:
Victryl's estimated overhead cost per labor hour was:
$700,000 / 35,000 = $20 per labor hour
If during February, Victryl had 5,000 direct labor hours, then its estimated cost should have been: $20 x 5,000 = $100,000 estimated overhead cost
The actual overhead cost was $98,300, which is $1,700 less than the estimated cost.