Answer:
a. $2.00
Step-by-step explanation:
The computation of the charge rate for Graphics production is shown below;
Charge rate = Graphics production cost ÷ total allocation
where,
Graphic production cost = $200,000
And the total allocation equal to
= Micro Number of copies made + Macro Number of copies made + Super Number of copies made
= 20,000 + 30,000 + 50,000
= 100,000
Now put these values to the above formula
So, the value would equal to
= $200,000 ÷ 100,00
= $2
As the cost driver is given in the question for graphics production i.e Number of copies made. So we consider it