Answer:
Actual rate of power generation = 7,544 KW
Step-by-step explanation:
given,
discharge of the hydroelectric power plant = 16.2 m³/s
elevation drop = 61 m
head loss through the intakes, penstock, and outlet works = 5.8 m
net head available = 61 - 5.8 = 55.2 m
power available
P = Q× (ρ g H)
P = 16.2 × (1000 × 9.81 × 55.2)
P = 8,772 KW
given efficiency = 86 %
so, Actual rate of power generation = 0.86 × 8772
Actual rate of power generation = 7,544 KW