Answer:
$1,000
Step-by-step explanation:
We know that
Total cost = Fixed cost + Variable cost
From the data given, we can calculate the variable cost using the high-low technique.
Variable cost per unit
=
=$15
Lease cost = FC + $15(Machine hours)
Lease cost -$15(Machine hours) = FC
Case,
i) 800 machine hours,
FC = Lease cost - $15(Machine hours)
= $16,000 -$15(1000) = $1,000