Answer:
Variable cost per unit= $300
Fixed cost= $1,750
Step-by-step explanation:
Giving the following information:
Month Maintenance Hours Maintenance Cost
June 11 $ 5,050
July 17 6,850
August 13 5,650
September 16 6,550
October 22 8,350
November 25 9,250
December 7 3,850
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
VCunit= (9250 - 3850) / (25 - 7)= 300 per hour
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 9250 - (300 * 25)= 1750
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 3850 - (300*7)= 1750