Answer:
The amount of manufacturing overhead would be allocated to Job 612 is $7,500
Step-by-step explanation:
The computation of the allocated manufacturing overhead is shown below:
= Predetermined overhead rate × Machine hours used
= $15 × 500 machine hours
= $7,500
Since in the question, it is mentioned that the Predetermined overhead rate based on machine hours so we multiply both the items for computing the allocated manufacturing overhead
Moreover, the formula to compute the predetermined overhead rate is shown below:
Predetermined overhead rate = (Total estimated manufacturing overhead) ÷ (estimated direct labor-hours)