Answer:
$256,284
Step-by-step explanation:
The computation is shown below:
First, Calculate the predetermined overhead rate per hour which equals to
= (Estimated manufacturing Overhead cost ÷ estimated machine hours)
= ($235,900 ÷ 20,800 hours)
= $11.34 per hour
So, the applied overhead or manufacturing overhead allocated equals to
= Predetermined overhead rate per hour × actual machine hours
= $11.34 per hour × 22,600 hours
= $256,284