Answer:
Total cost= $2520
Step-by-step explanation:
Giving the following information:
The Assembly Department uses a departmental overhead rate of $65 per machine hour, while the Sanding Department uses a departmental overhead rate of $15 per direct labor hour.
Job 603:
Assembly; 6 direct labor hours and 10 machine-hours.
Sanding; 3 direct labor hours and 9 machine hours.
The cost for direct labor is $25 per direct labor hour and the cost of the direct materials used by Job 603 is $1600.
Total cost= direct materials + direct labor + manufacturing overhead
Direct labor= 9*25= $225
Overhead= (10*65) + (3*15)= 695
Total cost= 1600 + 225 + 695= $2520