Answer:
The answer is: B) use the S-2 employee
Step-by-step explanation:
If you use an S-2 employee to make one unit of the product you are going to spend $7.60 [(24 min / 60 min) x $19].
If you use an S-1 employee to make one unit of the product you are going to spend $8.00 [(30 min / 60 min) x $16].
If you use an S-3 employee to make one unit of the product you are going to spend $7.70 [(21 min / 60 min) x $22].
Using an S-2 employee is the cheapest; $7.60.