Answer:
Total= $ 321.25
Step-by-step explanation:
Giving the following information:
Each surfboard consists of 30 separate parts totaling $ 155 direct materials and requires 3 hours of machine time to produce.
Materials handling: Number of parts $ 3.75 per part
Machining: Machine hours $ 2.00 per machine hour
Assembling: Number of parts $ 1.50 per part
Packaging: Number of finished units $ 2.75 per finished unit
Total manufacturing cost:
Direct materials= 155
Materials handling=$ 3.75* 30= $112.5
Machining: $ 2.00*3= 6
Assembling: $ 1.50*30= 45
Packaging: $ 2.75
Total= $ 321.25