Answer:
cut-off grade of the copper deposit. = 4.6 kg/ton 0r .46 % cu by weight
Step-by-step explanation:
Given data:
percentage of deposite copper is 0.80%
selling price of cu is $1.73/kg
overall unit cost = $6.5/ton
overall recovery 82%


= 11.3 $/ton
unit profit = (gross value - unit costs)
= (11.3 - 6.5)
=4.84 $/ton
cut off grade of copper deposit


= 4.6 kg/ton 0r .46 % cu by weight