HELP! Screen-printing a batch of shirts requires 4 minutes per shirt in addition to 6 minutes of initial set-up time. If it takes 46 minutes to screen-print a batch of shirts, how many shirts are in the batch?

User Hcura
by
7.5k points

2 Answers

4 votes

Answer:

10 shirts

Explanation:

46 = 6 + 4T

4T = 40

T = 10

User Md Isfar Uddin
by
7.0k points
4 votes
46-6(initial set up time)=40. 40/4=10 shirts