Answer:
applied overhead to hoses: 33,800
Step-by-step explanation:
We calculate the rate by dividing the expected overhead over the cost driver:

In this case, machine hours is the cost driver:
83,200 / 3,200 = 26
now applied ovehead:
machine hours x rate
1,300 x 26 = 33,800