205k views
2 votes
In step three of the five step composite risk management process, you will develop one or more controls that either eliminate the hazard or reduce the risk of a hazardous incident occurring. What type of controls take the form of individual and collective training, and performance to standards?

User DUDANF
by
8.3k points

1 Answer

0 votes

Answer:

Physical control

Explanation:

The risk to be ranked and prioritized. Most risk management has different of the risk, depending on the severity of the risk. A risk that may cause some inconveniences is rated as low. The risk-rated highly with catastrophic losses. It is rated to risk because it allows the organization to gain a holistic view of the risk exposure of the whole organization. The business may be more vulnerable to several low-risk factors. But it may not require upper management intervention. On the other hand, just one of the highest-rated risk is enough to require immediate intervention.

User Ram Rachum
by
8.1k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.