It took 6 people to paint several offices in 5 days. How many more people need to be hired to complete the same job in 3 days? Please include how to solve the question.

2 Answers

6 votes

Answer:

3.6

Explanation:

you can use a proportion for this. Since 6 people are painting several offices in 5 days you would put 6 over 5. now we have three numbers and we need to find how many people can complete the same job in three days. so we would put 3 across from 5 because there both the same label (day). we don't know the fourth number so put a x or variable any letter. we need to find x. after you set up your proportion you would then cross multiply . 6 times 3 is 18 and 5 times x is 5x. now we divide. 5 divided by 5x is just x or 1x. so you have x alone now. 18 divided by 5 is 3.6 so x is 3.6 which is the answer .

6people x

----------------------- 18/5 = 3.6

5days 3Days

User Pedro Massango
by
8.2k points
5 votes

Answer:

4 people

Explanation:

When
x_1 people complete a piece of work in
n_1 days and the same work is completed by
x_2 people in
n_2 days,

Then,


x_1* n_1=x_2* n_2

Here,


x_1=6,n_1=5, n_2 = 3

By substituting the values,


6* 5=3x_2


\implies x_(2)=(30)/(3) = 10

Thus, the additional number of people = 10 - 6 = 4

User Kevin Whinnery
by
7.8k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories