Which of these is NOT one of the four purposes of a project charter? a. Help the project manager, sponsor, and any team members that are already assigned develop a common understanding. b. Authorize the project manager to proceed c. Quickly screen out obviously poor projects d. Provide a detailed blueprint to guide project execution

User Acontell
by
7.8k points

1 Answer

5 votes

Answer:

The answer is: C) Quickly screen out obviously poor projects

Step-by-step explanation:

The statement "Quickly screen out obviously poor projects" has to do with a project´s evaluation stage, where it is determined if the project is positive and should be carried out or on the contrary it should be rejected.

A project charter serves as a reference document of an already approved project that is being carried out or will be carried out in the future.

User Manola
by
7.7k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories