Mickley Company’s plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $17.00 per hour. The following information pertains to Job A-500: Direct materials $ 231 Direct labor $ 153 Required: 1. What is the total manufacturing cost assigned to Job A-500?

User Miradham
by
5.9k points

1 Answer

6 votes

Answer:

Total manufacturing cost= $510

Step-by-step explanation:

Giving the following information:

Mickley Company’s plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $17.00 per hour. The following information pertains to Job A-500: Direct materials $ 231 Direct labor $ 153.

Direct labor hours= 153/17= 9 hours

Total manufacturing cost= direct material + direct labor + manufacturing overhead= 231+153 + (14*9)= $510