Answer:
Total manufacturing cost= $510
Step-by-step explanation:
Giving the following information:
Mickley Company’s plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $17.00 per hour. The following information pertains to Job A-500: Direct materials $ 231 Direct labor $ 153.
Direct labor hours= 153/17= 9 hours
Total manufacturing cost= direct material + direct labor + manufacturing overhead= 231+153 + (14*9)= $510