Answer:
leveled cost of electricity LCOE is 0.1159/kwh
Step-by-step explanation:
given data:
installation cost of system = $1.50/winstalled
capacity factor = 22%
life = 10 year
rate of interest 8%
operation and maintenance cost = $0.04 / kwh generated
capcaitence recovery factor

i= rate of interest
n = annuity period



= 0.1159/kwh + 0.04 /kwh
= 0.1559 /kwh