194k views
5 votes
Working alone at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6 hours, respectively. If the two machines work simultaneously at their respective constant rates, how many hours does it take the two machines to fill?

User Riywo
by
6.6k points

1 Answer

4 votes

Answer: 2 hours

Explanation:

Given : Working alone at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6 hours, respectively.

Let t be the time taken by both of them working together.

Then, according to the question, we have


(1)/(t)=(1)/(3)+(1)/(6)\\\\\Rightarrow(1)/(t)=(2+1)/(6)\ \ [\because\ L.C.M. (3,6)=6]\\\\\Rightarrow(1)/(t)=(3)/(6)=(1)/(2)\\\\\Rightarrow t=2

Hence, it will take 2 hours by the two machines .

User Dhasneem
by
6.8k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.