71.5k views
4 votes
A company had the following direct materials cost information:

Standard costs assigned: Direct materials standard cost (405,000 units @ $2/unit) $810,000

Actual costs: Direct Materials costs incurred (403,750 units @ $2.20/unit) $888,250

What was the cost variance?

a) $2,500 Favorable.
b) $78,250 Favorable
c) $78.250 Unfavorable
d) $80,750 Favorable.
e) $80,750 Unfavorable.

User Erion S
by
8.2k points

1 Answer

1 vote

Answer:

Option c) $78,250 unfavorable

Explanation:

The given information in the question :

Standard cost = $810,000

Actual cost = $888,250

Cost variance can be calculated as using the following formula :

Cost variance = standard cost - actual cost

= 810,000 - 888,250

= ($78,250) unfavorable

Favorable indicates how much under budget the project.

unfavorable indicates how much over budget the project.

Therefore, Option c) 78,250 unfavorable is the answer.

User AdelNick
by
8.4k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories