Answer:
The costs that should be assigned to the ending work-in process inventory is $102,000.
Step-by-step explanation:
the costs that should be assigned to the ending work-in-process inventory = $8×6000 + 0.75×$12×6000
= $102000
Therefore, the costs that should be assigned to the ending work-in process inventory is $102,000.