Answer: $9,200,000
Step-by-step explanation:
Input = 100,000 units
Ending work in progress = 8,000 units
Units that were completed and transferred out of the process:
= Input - Ending work in progress
= 100,000 - 8,000
= 92,000 units
Material Equivalence units = 8,000 x 100% + 92,000 x 100%
= 100,000 Equivalence unit
Cost of material per equivalence unit:
= $3/EU
Conversion cost Equivalence unit = 8,000 x 40% + 92,000 x 100%
= 3,200 + 92,000
= 95,200 units
Cost of conversion per equivalence unit:
= $3.375
Therefore,
The total amount of manufacturing costs assigned to those units that were completed and transferred out of the process in April:
= 92,000 x 40 + 92,000 x 60
= 3,680,000 + 5,520,000
= $9,200,000