Answer:
Applied overhead= $210,000
Step-by-step explanation:
Giving the following information:
Direct materials used $ 110,000.
Direct labor incurred (5,000 hours) $ 150,000
Actual manufacturing overhead incurred $ 166,000
Kilt Company used a predetermined overhead rate of $42.00 per direct labor hour.
Estimated direct labor hours would total 5,500 hours.
Assume the only inventory balance is an ending Work in Process balance of $17,000.
Applied overhead= overhead rate*actual direct labor hours
Applied overhead= 42*5000= $210,000