Answer:
The required workers will be 48
Step-by-step explanation:
The first step will be calcualte the rate of production per hour:
Rate: 150,000 / (50 wk x 10/wk x 7.5hr/shift) = 150,000/3750 = 40
Then the amount it takes to do a single unit:
Cicle: 60 minutes per hours x 0.95 efficiency / 40 units per hour:
1.425 minutes per unit
Then we include repositioning:
1.425 - repositioning: 8/60 = 1,291666666666667 min
The actual workers needed will be:
working time / balancing efficient x net cycle
58 minutes per worker / 0.93 (1,291666666666667) = 48