130k views
3 votes
Lakeside Company's schedule of cost of good manufactured include the following for April:Cost of Goods Manufactured $69,300Direct Materials Used $27,000Direct Labor Used $30,000Work in Process Inventory, April 1, 2005 $9,000Manufacturing overhead is applied for $8,000. Work in process inventory at April 30:

1 Answer

4 votes

Answer:

Work in process inventory at April 30 is $4,700

Step-by-step explanation:

In this question, we apply the cost of goods manufactured formula which is shown below:

Cost of goods manufactured = Opening balance of work in progress + total manufacturing cost - ending balance of work in progress

where,

Total manufacturing cost = Direct material + direct labor + overhead

= $27,000 + $30,000 + $8,000

= $65,000

So, the ending balance work in progress equal to

= $9,000 + $65,000 - $69,300

= $4,700

User Nikana Reklawyks
by
5.0k points