Which activity is not the responsibility of IT service continuity management?

A. Drawing up back-out scenarios

B. Analyzing risks

C. Testing back-out arrangements

D. Executing impact analyses of incidents related to the back-out facilities

User DongXu
by
8.3k points

1 Answer

5 votes

Answer:

D. Executing impact analyses of incidents related to the back-out facilities

Step-by-step explanation:

According to the ITIL manual, the activities for IT service continuity management are:

Identify services and assets,Identify risks and threats,Make contingency plans,Document the recovery plan