Answer: Option (c) is correct.
Step-by-step explanation:
Given that,
Beginning work in process = 20,000 units and 70% completed
So, Units transferred = 20,000 × 30%
= 6,000
Direct transferred = 80,000 units
Ending work in process = 10,000 × 40%
= 4,000
Therefore,
Units were transferred out of the process in June:
= Beginning WIP transferred + Direct transferred + Ending work in process
= 6,000 + 80,000 + 4,000
= 90,000 units