Answer: Option (d) is correct.
Step-by-step explanation:
The predetermined overhead is largely based on the estimations rather than actual costs. It is determined by dividing the total estimated factory overhead cost by the total number of estimated machine hours. It gives a way to the firms for measuring their factory overhead costs that are going high or low for a specific production run.