Compute the takt time for a service system that intended to perform a standardized service. The system will have a total work time of 366 minutes per day, two 18-minute breaks, and an hour for lunch. The service system must process 96 jobs a day. (Round your answer to 2 decimal places.)

Takt time ? minutes per cycle

1 Answer

1 vote

Answer:

3.81 minutes per cycle

Explanation:

Available production time is 366 minutes, during which time 96 jobs must be completed. The average time allowed per job is ...

366 min/(96 jobs) = 3.8125 min/job ≈ 3.81 minutes

Compute the takt time for a service system that intended to perform a standardized-example-1