Answer:
B) a, c, d, b
Step-by-step explanation:
a. Identify the primary activities and estimate a total cost pool for each.
c. Select an allocation base for each activity.
d. Calculate an activity cost allocation rate for each activity
b. Allocate the costs to the cost object using the activity cost allocation rates