Answer:
The total cost of Job 903 is $5,073.20
Step-by-step explanation:
The computation of the total cost is shown below:
= Direct material used + Direct labor cost + overhead cost (Predetermined manufacturing overhead rate per direct labor hour × Direct labor hours used in Job 903)
= $3,200 + $1,092 + ($18.60 × 42 labor hours)
= $3,200 + $1,092 + $781.20
= $5,073.20