Answer:
The probability that the project will be completed in 33 days or less is equal to 0.73.
Explanation:
The correct option is A:
Suppose that this is a normally distribution
The critical path length is 30 days .
i.e. Population mean = u=30
Variance: σ² = 25
Standard deviation = σ = √25 = 5
z-score: z = x-u/ σ
The value of z corresponding to 33 = z = 33-30/5
z = 3/5
z = 0.6
Now, the p-value = P(x≤33) = P(z≤0.6) = 0.7257469
By rounding off we get,
0.73
Thus the probability that the project will be completed in 33 days or less is equal to 0.73.