Answer:
Underapplied= $75000
Step-by-step explanation:
Giving the following information:
Carlisle Manufacturing expected Job No. 16 to cost $450,000 of overhead, $750,000 of materials, and $300,000 in labor.
Carlisle applied overhead based on direct labor cost.
Actual production:
Overhead cost =$420,000.
Direct materials= $825,000.
Direct labor= $330,000.
First, we need to calculate the overhead rate
Overhead rate= 450000/300000= 1.5 direct labor
Overhead according to rate:
330000*1.5= $495000
Real overhead= $420000
Underapplied= $75000