Answer:
a) 176.45
b) 141.2
Step-by-step explanation:
output 7,200
productivity: 0.12 van per labor hour
340 laborer employed
Where:
productivity = outpt/base
0.12 = 7,200/labor hours
7,200 / 0.12 = 60,000 total labor hours
Then we divide by the total laborers to know the average per laborer.
60,000/340 = 176.46 = 176.45 hours
(B) if the productivity increases to 0.15
then:
7,200/0.15 = 48,000
48,000 / 340 = 141.17 = 141.2