A process produces​ 6,000 units of output that yield​ $5.00 per unit. Resources contributed to this output are 200 hours of labor at​ $15.00 per​ hour, materials at​ $750, and overhead at​ $250. What is the labor productivity​ (in units per​ labor-hour)?

User Eunhee Ju
by
8.6k points

1 Answer

3 votes

Answer: 30 units per hour

Step-by-step explanation:

Given that,

Total number of product = 6,000 units

Yield = $5.00 per unit

Resources contributed to this output = 200 hours of labor at​ $15.00 per​ hour

Materials =​ $750

Overhead =​ $250

Labor productivity​ =
(Total\ number\ of\ product)/(Resources\ contributed)

=
(6,000)/(200)

= 30 units per hour