Among the​ following, critical path and slack time analysis MOST help A. point out who is responsible for various activities. B. highlight relationships among project activities. C. pinpoint activities that need to be closely watched. D. managers define the project activities.

2 Answers

2 votes

Final answer:

The correct answer is B. Slack time analysis helps highlight relationships among project activities.

Step-by-step explanation:

The correct answer is B. Slack time analysis helps highlight relationships among project activities. The critical path is the sequence of activities that must be completed in order to finish the project in the shortest possible time. It is determined by calculating the longest path through the project network diagram, which indicates the activities that have zero slack or float time. Slack time analysis helps identify the activities that have slack time, which is the amount of time that an activity can be delayed without affecting the project timeline. By analyzing the slack time, project managers can determine which activities are critical and which activities can be delayed without impacting the overall project schedule.

User Issiaka
by
4.7k points
2 votes

Answer:

The correct option is: D. pinpoint activities that need to be closely watched

Step-by-step explanation:

Critical path analysis, also known as the critical path method, is a method of project management that involves planning every important task necessary for the completion of the given project.

It also includes managing the time required for each and every task or activity, which tells about the associated slack time, used to predict the overall deadline of project completion.

Slack time analysis refers to the process of analyzing the delay in each task or activity without delaying the completion of the whole project.