Answer:
overhead rate: 17.5
Step-by-step explanation:
The difference between applied an actual overhead is calculated as follows:
actual hours x overhead rate - actual cost = over or underapplied overhead
underapplied means actual were higher than applied
while, overapplied means the actual cost were lower.
Based on this information we can set up the foermula as follows:
overhead rate x 32,000 -540,000 = 20,000
now we solve for the rate:
rate = (20,000 + 540,000) / 32,000 = 17.5