Venus Crates manufactures custom crates for a variety of uses. The following data have been recorded for Job​ 551, which was recently completed. Direct materials used cost​ $7,700. There were 90 machine hours used on this job. The predetermined overhead rate is​ $32 per machine hour used. There were 179 direct labor hours worked on this job at a direct labor wage rate of​ $31 per hour. What is the total manufacturing cost of Job​ 551?

User Addzo
by
4.7k points

1 Answer

5 votes

Answer:

Cost of goods manufactured= $16,129

Step-by-step explanation:

Total manufacturing cost is the aggregate amount of cost incurred by a business to produce goods in a reporting period.

Generally accepted accounting principles require that the cost of goods sold shall consist of:

the cost of direct materials

the cost of direct labor

the cost of manufacturing overhead

In this exercise:

Cost of goods manufactured:

Direct materials= $7,700

Direct Labor=179hours * $31=$5,549

Factory overhead= $32*90 hours= $2,880

Total= $16,129