47.8k views
2 votes
The following data have been recorded for recently completed Job 450 on its job cost sheet. Direct materials cost was $2,057. A total of 32 direct labor-hours and 216 machine-hours were worked on the job. The direct labor wage rate is $21 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $29 per machine-hour. The total cost for the job on its job cost sheet would be:

User Polynomial
by
5.8k points

1 Answer

3 votes

Answer:

Total cost= $8993

Step-by-step explanation:

Total manufacturing cost is the aggregate amount of cost incurred by a business to produce goods in a reporting period.

Generally accepted accounting principles require that the cost of goods sold shall consist of:

the cost of direct materials

the cost of direct labor

the cost of manufacturing overhead

In this exercise:

direct materials= $2057

direct labor= 32hours*$21=$672

manufacturing overhead= 216hours*$29= $6264

Total cost= 2057 + 672 + 6264= $8993