Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $3,400 of direct materials and used $4,900 of direct labor. The job was not finished by the end of the month, but needed an additional $3,900 of direct materials and additional direct labor of $7,400 to finish the job in October. The company applies overhead at the end of each month at a rate of 100% of the direct labor cost incurred. What is the total cost of the job when it is completed in October?

User Sgrgmngt
by
6.3k points

1 Answer

5 votes

Answer:

Total cost of Job A3B= $31,900

Step-by-step explanation:

Job A3B was ordered by a customer on September 25.

The company applies overhead at a rate of 100% of the direct labor cost incurred.

Cost of September:

$3,400 of direct materials

$4,900 of direct labor.

$4,900 manufactured overhead

Total= $13,200

Cost of October:

$3,900 of direct materials

$7,400 of direct labor

$7,400 manufactured overhead

Total= $18,700

Total cost of Job A3B= 13,200 + 18,700= $31,900