Answer:
1) the correct answer is D= $288
2) the correct answer is= $162000
Step-by-step explanation:
A)
Overhead applied during the whole year:
$24,000
Direct hours= 10000
Unitary overhead= 24000/10000= $2,4hour
Job 3 took 120 hours
Over head= 120*2,4= $288
B)
To calculate the cost of manufactured goods we need to use the following formula:
Cost of good manufactured= Beginning work in progress+ direct materials of the period + direct labor + manufactured overhead - ending work in progress
Beginning work in progress= $17000
Direct materials = 72000
Direct labor= 80000
Manufactured overhead=24000
Ending work in progress= 31000
Cost of good manufactured= 17000+72000+80000+24000-31000= $162000