A new sidewalk will be 5 feet​ wide, 100 feet​ long, and filled to a depth of 3 inches ​(0.25 ​foot) with concrete. How many cubic yards of concrete are​ needed?

1 Answer

7 votes

Answer:

4.63 cubic yard.

Explanation:

Given,

The length of sidewalk, l = 100 feet,

Width, w = 5 feet,

Depth, h = 3 inches = 0.25 feet,

Thus, the volume of the concrete needed for making the sidewalk,


V=l* w* h


=100* 5* 0.25

= 125 cubic feet,

∵ 1 cubic yard = 27 cubic feet,

⇒ 1 cubic feet =
(1)/(27) cubic yard,

Thus, the quantity of concrete needed =
(125)/(27)4.63 cubic yard.