Answer:
Project A
Step-by-step explanation:
Given:
The payback period for the project A = 18 months
Cost of project B = $125,000
Expected cash flow for the first year for the project B = $50,000
Cash flow per quarter after first year = $25,000
Now,
Remaining cost for project B after the first year payment
= $125,000 - $50,000
= $75,000
payback period for the project B after the first year
=
=
= 3 quarters = 9 months
therefore,
the total payback period for project B = 1 year + 9 months = 21 months
hence, Project A should be recommended as the payback period for project A is less i.e 18 months