Answer:
It explicitly incorporates uncertainty in one or more input variables.
Step-by-step explanation:
In simulation analysis we perform 1000's of calculations assigning risk of uncertainty to multiple input variables, as with increased data set the variable tend to increase.
This technique is generally used, for project management and further, decision making in many streams.
Under this probability of different results in the form of outcomes are evaluated.
Therefore, the correct statement is b.