Answer:
$5.32 per Machine hours
Step-by-step explanation:
Data provided:
Estimated manufacturing overhead = $532,000
Estimated direct labor hours = 25,000
Estimated machine hours (MHR) = 100,000
Now,
Since, the managers allocated the overhead based on the machine hours
therefore,
the predetermined manufacturing rate for the coming year will be
=

or
=

or
= $5.32 per Machine hours