In December ,General Motors produced 7,200 customized vans at its plant in Detroit. The labor productivity at this plant is known to have been 0.10 vans per labor hour during that month, 340 laborers were employed at the plant that month.A. In the month of December the average number of hours worked per laborer?B. If productivity was increased to 0.15 vans per hour, the average number of hours worked per laborer?

User Sugunan
by
4.8k points

2 Answers

4 votes

Answer:

A) The number of hours per worker during December= 211,76 hours

B) The number of hours per worker during December=141,18 hours

Step-by-step explanation:

In December, General Motors produced 7,200 customized vans at its plant in Detroit.

The labor productivity at this plant is known to have been 0.10 vans per labor hour during that month

340 laborers were employed at the plant that month.

A)

Considering that each worker produces 0,10 van an hour.

340workers*0,10=34vans per hour

The number of hours per worker during December= 7200vans/34vans= 211,76 hours

B) Labor productivity increases to 0,15 vans per hour per worker.

340workers*0,15= 51vans/hour

The number of hours per worker during December= 7200vans/51= 141,18 hours

User Arcass
by
5.0k points
5 votes

The average number of hours worked per laborer is 211.76 hours and when productivity is increased the average number of hours worked per laborer is 141.18 hours.

What is Productivity?

Generating a measure used to measure how well an organization (or individual, industry, country) effectively transforms inputs (workers, building materials, machinery, etc.) into goods and services. This is usually expressed in terms of output inputs.

As per the given information, In December, General Motors manufactured 7,200 customized vans for its factory in Detroit. The production of staff at the facility is known to have been 0.10 vans per hour of work per month. 340 factory workers were hired that month.

A) It is estimated that each worker produces 0.10 vans per hour:


\rm\,340\,workers*0.10 = 34vans\,per\,hour\\Average\,Number\,of hours\,per job = (\rm\,7200\,vans)/(\rm34vans) = \rm\,211.76 hours

B) Labor productivity increases to 0.15 vans per hour per job:


\rm\,340\,workers*0.15 = 51vans\,per\,hour\\\\Average\,Number\,of hours\,per job = (\rm\,7200\,vans)/(\rm51vans) = \rm\,141.18 hours

Hence, The average number of hours worked per laborer is 211.76 hours and when productivity is increased the average number of hours worked per laborer is 141.18 hours.